Description of works Excavation worksSurface grading, leveling, compaction with rollerConstruction of internal access roadsConcrete productionConstruction of micropilesFencing works Project details: Contractor : VEGA ENERGYSubcontractor: DEHA 2010 shpkTimeline : 2023-Continuous Previous project Civil works for the 2.4MW & 4.8MW Photovoltaic Park in Darëzezë, Fier Next project Infrastructure "Green Coast 2"
Intervention for the improvement of protective structures, work of art, in Nikolice-Arrez segment.July 1, 2024